  • AGENDA - 10/01/2019 -  CI BluePrint Validation SubCommettee - Meeting

    Lab Status

    • Community Lab Updates from Lincoln Lavoie

    Release 2 BluePrint CI Planning


  • AGENDA 9/24/2019 -  CI BluePrint Validation SubCommettee - Meeting Notes

    Lab Status: Ampere Hardware

    • 3 Servers were received by UNH
    • Servers are currently racked.
    • Cables were received today, and server will be finished cabling by end of day 9/24/2019.
    • Centos 7.6 AARCH64 will be installed on the Ampere equipment.
    • Servers should be ready by end of day 9/26/2019
    • Were able to get Sonic installed on the EdgeCore switches however they ran into a problemCommunity Lab Updates from Lincoln Lavoie

    Release 2 BluePrint CI Planning

    • Connected Vehicle

      Blueprint CI Discussion​

      BluePrint CI Discussion

      • Work with Lincoln's team to get named user list for vpn access to ampere equipment once equipment has finished being provisioned.

    Release 2 BluePrint CI Planning

    • IEC Type 1 for Integrated Edge Cloud (IEC)

      Blueprint

      BluePrint Family

       CI Discussion

      CI Discussion

      • Requirement 10G networking

      • Will supply url to presentation with remaining HW requirements.


  • 9/17/2019 -  CI BluePrint Validation SubCommettee - Meeting  Notes

    Lab Status

    • Hardware Request​ed and 3 Servers shipped from Ampere to UNH Interop Lab
    • Server should arrive at lab by 09/18/2019
    • Estimated that servers will be operational by CI meeting on 9/24

    Discuss adding a Ci SubCommettee co-chair 

    • Meeting participates unamanously aggreed on adding Robert Qiu who is responsible for APAC blueprint validation lab setup as co-chair to the CI SubCommittee.
    • Follow up sent by Peter to Deepak for procedures to verify co-chair

    Release 2 Planning 

    • Schedule time with each R2 blueprint PTL to discuss CI requirements.
    • Information gathering exercise for the purpose of planning, scheduling, and ensuring adequate resources are available.
    • Schedule discussed at Tuesday TSC Meeting
    • Schedule:

...