  1. Reviewed status progress
  2. Subcomittee review delierables status
    1. Documentation
      1. Follow R3 document structure and have first level document before next Monday - Srini
      2. Next week plan for document review based on progress (adhoc meeting during next week)
    2. Security
      1. Vuls is approved - Link to be added - Srini
      2. Lyns is approved - Have verbal confirmation from WG
      3. Kube-Hunter - One pending issue need further discussion with WG
    3. Validation
      1. Approval is there - Link to be added - Srini
    4. API
      1. API is approved - Link to be added - Gaurav - Blueprint Projects R4 API Reporting Requirements
    5. TSC
      1. Logs needs to be pushed to nexus - Srini
      2. Datasheet to be prepared - Open
      3. 10th December is scheduled date
    6. Upstream – ??
Agenta and MOM:  

...