Comment: 18 Jan progress report

...

  • Progress report:
    • Phase 3, basic inter-node communication, complete 1/7 (1wk delay)
    • Update of tasks for release in progress
    • Phase 4, LoRa and sensor integration, LoRa hardware arrives 1/11, sensor hardware 1/17
    • Preparing materials for Device and Device SDK Working Group (next Monday)

Weekly Meeting  

  • Progress report:
    • Phase 4, LoRa and sensor integration, in progress, planned completion 1/25
    • Tasks for release 6 listed in progress report (slide 9): Documents, API form, BluVal + security checks are main items
    • The full lab setup is configured and now we are working on device support and a pass-through app on the sensor nodes
    • We'd like to build a second lab setup but need to add two more Raspberry Pi devices for that, also LoRa dongles if possible (meet with Fukano-san on Wednesday to discuss further)