Please go to R2 page for Rel 2 BP incubation Stage Milestone Reporting
PTL TSC Presentation Criteria
1) Is a validation lab in place?
2) Has a code repository been established?
3) Have regular meetings been scheduled?
4) Has a backlog been established?
5) Have any issues been identified that require support from the TSC?
Incubation stage reporting
MBI = Milestone Bp Incubation
...
Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.
Project Name | MBI0 Project |
---|
Induction | MBI1 |
---|
Kick Off | MBI2 Planning |
---|
Identify integration/developers team & testing team
Identify whether LF CD or external validation lab to be used for first validation.
MBI3
Integration Test plan created and shared with the community
Requirement/Feature Freeze (if applicable)
MBI4
Additional test scripts development and Set up accessible
Lab is set up for CD
process defined | MBI3 CD Test Scripts developed 1st Validation Lab is Set up | MBI4 First Full CD deployment BP is ready to download and deployable by users as self certified |
---|
MBI5
Code Freeze (if applicable)
Additional test case development complete
MBI6
First deployment in validation lab
First test report logs shipped to LF CI serversAd hoc reporting CI/CD based testing |
---|
MBI7
Second community validation lab identified
and bug fixing | MBI5 Second community validation lab fully setup |
---|
MBI9
BP successfully deployed in second community validation lab
MBI10
Critical issues fixed.
Documentation complete for other community member(s) to deploy identical validation lab
MBI6 Ready for Maturity Review | Maturity Graduation Review as per BP Graduation Review Processes and Criteria |
---|
(Request for graduation review made by PTL |
---|
) |
---|
TSC's Graduation review can have one of two outcomes:
- Project remains at 'Incubation' (i.e. the request to graduate wasn't approved by the TSC)
- Project graduates from 'Incubation' to 'Mature' (i.e. the request to graduate was approved by the TSC)
1 |
12/7/2019 | Target date |
Feb 2, 2019 | April 22, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date |
Feb 2, 2019 | |||||||
2 | Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family | 12/7/2019 | Target date |
Achieved date |
3 |
12/7/2019 | Target date |
Achieved date |
Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||
4 | 12/7/2019 | Target date |
Achieved date |
Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | |||
5 | 12/7/2019 | Target date |
Feb 8,2019 | March 13,2019 | May 3, 2019 | May 30, 2019 | |||||
Achieved date | Feb 8,2019 | March 13,2019 | April 29, 2019 | May 26, 2019 |
6 | 12/7/2019 | Target date |
Achieved date |
7 | 12/7/2019 | Target date |
Mar 23, 2019 | Mar 29, 2019 | Apr 22, 2019 | May 30, 2019 | May 31, 2019 | ||||
Achieved date |
Mar 23, 2019 | Mar 29, 2019 | ||||||
8 | 12/7/2019 | Target date |
Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | ||||
Achieved date |
9 | 12/7/2019 | Target date |
Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | ||||
Achieved date |
10 | 12/7/2019 | Target date |
Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | |||
Achieved date |
Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||
11 | 12/7/2019 | Target date |
Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 |
12 | 12/7/2019 | Target date |
Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 https://jenkins.akraino.org/view/kni/ | Jun 30, 2019 | Jun 30, 2019 | ||||
Achieved date |
Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | ||||||
13 | 12/7/2019 | Target date |
Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 https://jenkins.akraino.org/view/kni/ | May 30, 2019 | Jun 30, 2019 | |||
Achieved date |
Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | May 27, 2019 | ||||
14 | 12/7/2019 | Target date |
2019-03-12 | 2019-05-20 | 2019-05-15 | 2019-05-30 | 2019-05-10 | 2019-05-30 | |||
Achieved date |
2019-03-12 | 2019-05-28 | 2019-05-28 | 2019-05-28 | |||||
15 | 12/7/2019 | Target date |
2019-03-04 | 2019-05-03 | 2019-05-28 | 2019-05-28 | |||||
Achieved date | 2019-03-04 | 2019-05-03 | 2019-06-04 | 2019-06-04 |
16 | 12/7/2019 | Target date |
Achieved date |
17 | Target date | ||||||||||
Achieved date |
18 | 12/4/2019 | Target date | April 12, 2019 | June 12, 2019 | Sep 12, 2019 | Oct 12,2019 | |||||
Achieved date | |||||||||||
19 | 4/25/2019 | Target date | May 10, 2019 | June 6, 2019 | August 12, 2019 | October 12, 2019 | November, 12 2019 | TBD | TBD | ||
Achieved date | May 10, 2019 | ||||||||||
20 | |||||||||||
21 |
CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED
...
MBI | Name | Description/Checklist | |||
---|---|---|---|---|---|
MBI0 | Project Induction | Blue Print Kick Offis voted by TSC as an Akraino Blueprint. The project is defined and approved by TSC vote to enter incubation stage (Incubation Review) | |||
MBI1 | Kick Off | First First regular community call held Recurring , Recurring meeting should have been setup and details appear in the BP community meeting calendar: https://lists.akraino.org/g/blueprints/calendar. The first meeting date would be the timestamp for the 'Achieved date'. | |||
MBI2 | Planning completeCD lab identifiedProcess Defined |
| |||
MBI3 | Additional Test scripts development CD lab is setup |
| MBI4 | Test scripts development LF lab for CD setup and accessible if using LF lab for CD External validation lab is set up for CD if using external lab |
|
MBI5 | Code Freeze (if applicable) Additional test case development complete |
| |||
MBI4 | First Full CD deployment |
| MBI6 | First deployment in validation lab First testing logs shipped |
|
Ad hoc reporting | On going CI/CD Not really a milestone but an on going reporting period | Ad hoc reporting milestone is dependent on MBI6 Unlike the other milestones this milestone is a continuous one that spans from the start of testing (MBI6) as long as required by the CI/CD process until the BP is ready for the Maturing review by the TSC.
| |||
MBI7 MBI5 | Second community validation lab identifiedlab fully setup |
Part of the graduation requirements from incubation to mature require deployment in at least 2 community labs | MBI8 | Second community validation lab fully setup
| |
MBI9 MBI6 | BP successfully deployed in second community validation lab | All test cases planned for the release have been executed . Deployment in second lab may result in CI/CD iterations of the BP depending on results/experiences with the second setup. | |||
MBI10 | CI/CD based testing completed in all target validation labs Critical issues fixed. Documentation complete (for third parties to recreate setup and run the tests) | MBI10 is dependent on MBI6 and MBI9
| |||
Maturity Graduation review | TSC conducts graduation review as per criteria set out in Akraino Project Reviews Remove This Page 2 | Request for graduation review made by PTL Decision of graduation made TSC TSC's Maturity Graduation review can have one of two outcomes:
|