Please go to R2 page for Rel 2 BP incubation Stage Milestone Reporting
PTL TSC Presentation Criteria
1) Is a validation lab in place?
...
5) Have any issues been identified that require support from the TSC?
Incubation stage reporting
MBI = Milestone Bp Incubation
...
Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.
Project Name | MBI0 Project Induction | MBI1 Kick Off | MBI2 Planning process defined | MBI3 CD Test Scripts developed 1st Validation Lab is Set up | MBI4 First Full CD deployment BP is ready to download and deployable by users |
---|
User document.
as self certified | Ad hoc reporting CI/CD based testing and bug fixing | MBI5 Second community validation lab fully setup | MBI6 |
---|
Ready for Maturity Review | Maturity Graduation Review as per BP Graduation Review |
---|
(Request for graduation review made by PTL) | |
---|---|
1 |
12/7/2019 | Target date | Feb 2, 2019 | April 22, 2019 | May 30, 2019 | Jun 30, 2019 | ||||||
Achieved date | Feb 2, 2019 | ||||||||||
2 | Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family | 12/7/2019 | Target date | ||||||||
Achieved date | |||||||||||
3 |
12/7/2019 | Target date | ||||||||||
Achieved date | Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||||
4 | 12/7/2019 | Target date | |||||||||
Achieved date | Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||||
5 | 12/7/2019 | Target date | Feb 8,2019 | March 13,2019 | May 3, 2019 | May 30, 2019 | |||||
Achieved date | Feb 8,2019 | March 13,2019 | April 29, 2019 | May 26, 2019 | |||||||
6 | 12/7/2019 | Target date | |||||||||
Achieved date | |||||||||||
7 | 12/7/2019 | Target date | Mar 23, 2019 | Mar 29, 2019 | Apr 22, 2019 | May |
30, 2019 | May 31, 2019 | ||||||||||
Achieved date | Mar 23, 2019 | Mar 29, 2019 | |||||||||
8 | 12/7/2019 | Target date | Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | |||||
Achieved date | |||||||||||
9 | 12/7/2019 | Target date | Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | |||||
Achieved date | |||||||||||
10 | 12/7/2019 | Target date | Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||||
11 | 12/7/2019 | Target date | Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||||
12 | 12/7/2019 | Target date | Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 https://jenkins.akraino.org/view/kni/ | Jun 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | ||||||||
13 | 12/7/2019 | Target date | Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 https://jenkins.akraino.org/view/kni/ | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | May 27, 2019 | |||||||
14 | 12/7/2019 | Target date | 2019-03-12 | 2019-05-20 | 2019-05-15 | 2019-05-30 | 2019-05-10 | 2019-05-30 | |||
Achieved date | 2019-03-12 | 2019-05-28 | 2019-05-28 | 2019-05-28 | |||||||
15 | 12/7/2019 | Target date | 2019-03-04 | 2019-05-03 | 2019-05-28 | 2019-05-28 | |||||
Achieved date | 2019-03-04 | 2019-05-03 | 2019-06-04 | 2019-06-04 | |||||||
16 | 12/7/2019 | Target date | |||||||||
Achieved date | |||||||||||
17 | Target date |
Achieved date | |||||||||
18 |
12/4/2019 | Target date | April 12, 2019 | June 12, 2019 | Sep 12, 2019 | Oct 12,2019 | ||||||
Achieved date | |||||||||||
19 | 4/25/2019 | Target date | May 10, 2019 | June 6, 2019 | August 12, 2019 | October 12, 2019 | November, 12 2019 | TBD | TBD | ||
Achieved date | May 10, 2019 | ||||||||||
20 | |||||||||||
21 |
CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED
...
MBI | Name | Description/Checklist |
---|---|---|
MBI0 | Project Induction | Blue Print is voted by TSC as an Akraino Blueprint. The project is defined and approved by TSC vote to enter incubation stage (Incubation Review) |
MBI1 | Kick Off | First regular community call held, Recurring meeting should have been setup and details appear in the BP community meeting calendar: https://lists.akraino.org/g/blueprints/calendar. The first meeting date would be the timestamp for the 'Achieved date'. |
MBI2 | Planning Process Defined |
|
MBI3 | Additional Test scripts development CD lab is setup |
|
MBI4 | First Full CD deployment |
|
Ad hoc reporting | On going CI/CD Not really a milestone but an on going reporting period | Ad hoc reporting milestone is dependent on MBI6 Unlike the other milestones this milestone is a continuous one that spans from the start of testing (MBI6) as long as required by the CI/CD process until the BP is ready for the Maturing review by the TSC.
|
MBI5 | Second community validation lab fully setup |
|
MBI6 | BP successfully deployed in second community validation lab | All test cases planned for the release have been executed . Deployment in second lab may result in CI/CD iterations of the BP depending on results/experiences with the second setup. |
Maturity Graduation review | TSC conducts graduation review as per criteria set out in Remove This Page 2 | Request for graduation review made by PTL Decision of graduation made TSC TSC's Maturity Graduation review can have one of two outcomes:
|
...