Please go to R2 page for Rel 2 BP incubation Stage Milestone Reporting
PTL TSC Presentation Criteria
1) Is a validation lab in place?
...
5) Have any issues been identified that require support from the TSC?
Incubation stage reporting
MBI = Milestone Bp Incubation
...
Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.
Project Name | MBI0 Project Induction | MBI1 Kick Off | MBI2 Planning process defined | MBI3 CD Test Scripts developed 1st Validation Lab is Set up | MBI4 First Full CD deployment BP is ready to download and deployable by users |
---|
User document.
as self certified | Ad hoc reporting CI/CD based testing and bug fixing | MBI5 Second community validation lab fully setup | MBI6 |
---|
Ready for Maturity Review | Maturity Graduation Review as per BP Graduation Review |
---|
(Request for graduation review made by PTL) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
1 | SDN Enabled Broadband Access (SEBA) for Telco Appliance Blueprint Family | 12/7/2019 | Target date | Feb 2, 2019 | April 22, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Feb 2, 2019 | ||||||||||
2 | Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family | 12/7/2019 | Target date | ||||||||
Achieved date | |||||||||||
3 |
12/7/2019 | Target date | ||||||||||
Achieved date | Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||||
4 | 12/7/2019 | Target date | |||||||||
Achieved date | Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||||
5 | 12/7/2019 | Target date | Feb 8,2019 | March 13,2019 | May 3, 2019 | May 30, 2019 | |||||
Achieved date | Feb 8,2019 | March 13,2019 | April 29, 2019 | May 26, 2019 | |||||||
6 | 12/7/2019 | Target date | |||||||||
Achieved date | |||||||||||
7 | 12/7/2019 | Target date | Mar 23, 2019 | Mar 29, 2019 | Apr 22, 2019 | May |
30, 2019 | May |
31, 2019 | |||||||||||
Achieved date | Mar 23, 2019 | Mar 29, 2019 | |||||||||
8 | 12/7/2019 | Target date | Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | |||||
Achieved date | |||||||||||
9 | 12/7/2019 | Target date | Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | |||||
Achieved date | |||||||||||
10 | 12/7/2019 | Target date | Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||||
11 | 12/7/2019 | Target date | Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||||
12 | 12/7/2019 | Target date | Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 |
https://jenkins.akraino.org/view/kni/ |
Jun 30, 2019 | Jun 30, 2019 | |||||||
Achieved date | Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | |||||
13 | 12/7/2019 | Target date | Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 |
https://jenkins.akraino.org/view/kni/ | May 30, 2019 | Jun 30, 2019 | |||||||||
Achieved date | Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | May 27, 2019 | |||||||
14 | 12/7/2019 | Target date | 2019-03-12 | 2019-05-20 | 2019-05-15 | 2019-05-30 | 2019-05-10 | 2019-05-30 | |||
Achieved date | 2019-03-12 | 2019-05-28 | 2019-05-28 | 2019-05-28 | |||||||
15 | 12/7/2019 | Target date | 2019-03-04 | 2019-05-03 | 2019-05-28 | 2019-05-28 | |||||
Achieved date | 2019-03-04 | 2019-05-03 | 2019-06-04 | 2019-06-04 | |||||||
16 | 12/7/2019 | Target date | |||||||||
Achieved date | |||||||||||
17 | Target date |
Achieved date | |||||||||
18 |
12/4/2019 | Target date | April 12, 2019 | June 12, 2019 | Sep 12, 2019 | Oct 12,2019 | ||||||
Achieved date | |||||||||||
19 | 4/25/2019 | Target date | May 10, 2019 | June 6, 2019 | August 12, 2019 | October 12, 2019 | November, 12 2019 | TBD | TBD | ||
Achieved date | May 10, 2019 | ||||||||||
20 | |||||||||||
21 |
CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED
...