Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Please go to R2 page for  Rel 2 BP incubation Stage Milestone Reporting

PTL TSC Presentation Criteria

1) Is a validation lab in place?

2) Has a code repository been established?

3) Have regular meetings been scheduled?

4) Has a backlog been established?

5) Have any issues been identified that require support from the TSC?


Incubation stage reporting

 MBI = Milestone Bp Incubation

...

4) There are sequential milestones (S) and non sequential milestones (NS). The non sequential milestones are guidelines to be completed at a certain stage, however they are not gating factors to enter the next or a subsequent stage. However the NS milestones also need to be completed at some point which will be marked as part of the relevant stage.

The graduation reviews are done by assessing the projects the projects against the Incubation to Mature review as defined in the Akraino Project Reviews page.


Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.



Project Name

MBI0

Project

inducted to 'Incubation' by TSC

Induction


MBI1

First regular community call held

Kick Off

MBI2

Planning

completeIdentify integration/developers team & testing team

process defined


MBI3

Integration Test plan created and shared with the community

Requirement/Feature Freeze (if applicable)

CD Test Scripts developed

1st Validation Lab is Set up


MBI4

First Full CD deployment

BP is ready to download and deployable by users as self certified

MBI4

Scripts development and Set up accessible

Lab is set up for CD

MBI5

Code Freeze (if applicable)

Additional test case development complete (

MBI6

First deployment in validation lab

First test report logs shipped to LF CI servers

Ad hoc reporting

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

and bug fixing


MBI5

MBI7

Second community validation lab identified

MBI8

Second community validation lab fully setup

MBI9

BP successfully deployed in second community validation lab

MBI6

Ready for Maturity Review

Maturity Graduation Review as per BP Graduation Review Processes and Criteria

Graduation Review by TSC

(Request for graduation review made by PTL)

(Decision of graduation made TSC)

TSC's Graduation review can have one of two outcomes:

  1. Project remains at 'Incubation' (i.e. the request to graduate wasn't approved by the TSC)
  2. Project graduates from 'Incubation' to 'Mature' (i.e. the request to graduate was approved by the TSC)
1

SDN Enabled Broadband Access (SEBA) for

Network Cloud

Telco Appliance Blueprint Family

x

Aaron Byrd

12/7/2019

Target dateFeb 2, 2019April 22, 2019May 30, 2019Jun 30, 2019



Achieved dateFeb 2, 2019






2

Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family

x

Itamar Eshet

12/7/2019

Target date







Achieved date







3

Unicycle

Blueprint Proposal for Addition to Network Cloud Blueprint Familyx

with SR-IOV Project

David Plunkett

12/7/2019

Target date







Achieved dateFeb 11, 2019Apr 29, 2019Aug 22, 2018Aug 22, 2018Feb 11, 2019


4

Rover Blueprint Proposal for Addition to Network Cloud Blueprint Family

x

David Plunkett

12/7/2019

Target date







Achieved dateFeb 11, 2019Apr 29, 2019Aug 22, 2018Aug 22, 2018Feb 11, 2019


5

OVS-DPDK Unicycle Dell Blueprint Proposal

x

Rakesh Bohra

12/7/2019

Target dateFeb 8,2019March 13,2019May 3, 2019May 30, 2019



Achieved dateFeb 8,2019March 13,2019April 29, 2019May 26, 2019



6

NC-TF-BluePrint-ProposalAkraino Network Cloud and TF Integration

x

Sukhdev Kapur

12/7/2019

Target date







Achieved date







7
x

12/7/2019


Target dateMar 23, 2019Mar 29, 2019Apr 22, 2019May 30, 2019May 31, 2019


Achieved dateMar 23, 2019Mar 29, 2019





8
x
12/7/2019Target dateFeb 27, 2019Apr 30, 2019May 10, 2019May 30, 2019



Achieved date







9
x
12/7/2019Target dateFeb 27, 2019Apr 30, 2019May 10, 2019May 30, 2019



Achieved date







10

IEC Type 1 for Integrated Edge Cloud (IEC) Blueprint Family

x

Trevor Tao

12/7/2019Target dateJan 28, 2019 Feb 05, 2019Apr 15, 2019May 30, 2019Jun 30, 2019


Achieved dateJan 28, 2019 Feb 05, 2019Apr 2, 2019

May 21, 2019

IEC Release 1 Documentation





11

IEC Type 2 for Integrated Edge Cloud (IEC) Blueprint Family

x

xinhuili

12/7/2019Target dateJan 28, 2019 Feb 05, 2019Apr 15, 2019May 30, 2019Jun 30, 2019


Achieved dateJan 28, 2019 Feb 05, 2019

Apr 2, 2019

https://jenkins.akraino.org/view/iec/

May 21, 2019

IEC Release 1 Documentation





12

Industrial Edge (IE) Blueprint

xAchieved date

Yolanda Robla Mota

12/7/2019Target dateFeb 11,
2019
Apr 30,
2019
May 5, 2019
https://jenkins.akraino.org/view/kni/
Jun 30, 2019Jun 30, 2019


Achieved dateFeb 11,
2019
Apr 30,
2019
May 3, 2019




13

Provider Access Edge (PAE) Blueprint

xTarget date

Yolanda Robla Mota

12/7/2019Target dateFeb 11,
2019
Apr 30,
2019
May 5, 2019
https://jenkins.akraino.org/view/kni/
May 30, 2019Jun 30, 2019


Achieved dateFeb 11,
2019
Apr 30,
2019
May 3, 2019May 27, 2019



14

Radio Edge Cloud

x

Paul Carver

12/7/2019Target date2019-03-122019-05-202019-05-152019-05-30
2019-05-102019-05-30
Achieved date2019-03-122019-05-282019-05-282019-05-28



15

StarlingX Far Edge Distributed Cloud

x

Bill Zvonar

12/7/2019Target date2019-03-042019-05-032019-05-282019-05-28



Achieved date2019-03-042019-05-032019-06-042019-06-04



16

Time-Critical Edge Compute

x

Shane Dewing

12/7/2019Target date







Achieved date







17

Micro-MEC

Tapio Tallgren


Target date








Achieved date







18

Connected Vehicle Blueprint

xin qiu

12/4/2019Target date

April 12,

2019

June 12,

2019

Sep 12, 2019

Oct 12,2019





Achieved date







19

IEC Type 4 for Integrated Edge Cloud (IEC) Blueprint Family

Wenhui Zhang

 4/25/2019

Target dateMay 10, 2019June 6, 2019August 12, 2019October 12, 2019November, 12 2019TBDTBD
Achieved dateMay 10, 2019






20









21

Integrated Cloud Native NFV/App stack family (Short term: ICN)

Kuralamudhan Ramakrishnan












CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED


MBI

Name

Description/Checklist

MBI0Project InductionBlue Print
Kick Off
is voted by TSC as an Akraino Blueprint. The project is defined and approved by TSC vote to enter incubation stage (Incubation Review)
MBI1
Planning complete
  • Projects that have successfully completed MS0, must complete their planning, including scenario or deliverable definition.
  • Kick Off First regular community call held, Recurring meeting should have been setup and details appear in the BP community meeting calendar: https://lists.akraino.org/g/blueprints/calendar. The first meeting date would be the timestamp for the 'Achieved date'.
    MBI2

    Planning Process Defined

    • MBI2 is dependent on MBI1
    • Identify integration/developers team & testing team
    • Identify whether LF CD or external validation lab is to be used for first validation
    As part of the planning process, all projects will complete a project planning template
    • .
    • hardware set up definition frozen
    (NS)
    • and clearly and fully published to the community such that any community member can replicate
    • Identify team working on features & testing
    (NS)
  • Paid Jenkins Set up (NS)
  • MBI2

    Integration Test plan created and shared with the community

    Requirement/ Feature Freeze (if applicable)

    • Requirement/Feature freeze if there is code contribution as part of the blueprint or the upstream (All features are identified and JIRA stories created)
    • Comprehensive test plan documentation is created
    • hardware set up definition frozen ( NS)
    • Document the lab setup required and identify the labs that would be used to test this blueprint. If the lab is third party lab, get the lab reserved.
    • Security:<TBF>
    MBI3

    Scripts development and Set up accessible

  • Make scripts available to create setups in third party labs.
  • Make the setups accessible for everybody (optional).
    MBI3

    Additional Test scripts development

    CD lab is setup

    • All  additional test cases beyond those defined as mandatory for each layer being deployed by the BP are automated if possible and made available in blueprint repos.
    • If LF lab is used for CD
      • The set up is complete and is accessible
      • Instructions to access the setup including the method
    Instructions to access the setups. Method
      • to reserve/un-reserve
    setups. Preferably two setups at-least.
  • Security: <TBF>
  • MBI4

    Code Freeze (if applicable)

    Test case development complete

    • Integration complete of all SW packages that are part of the blueprint
    • All test cases are automated and made them available in blueprint repos.
    • Make the images available in public repository (Nexus?) and create scripts to necessary to install all SW packages in various sites as identified by blueprint
      • hardware are available.
    • If member validation lab is being used for CD
      • All HW required to deploy the BP has been installed and is ready to start CD of actual BP
    • Peer Jenkins Set up in case of external validation lab (CI, Blueprint Validation Lab sub-committee
    • Security: <TBF>
    MBI4

    First Full CD deployment

    • All requirements up till MBI4 
    MBI5

    first deployment in validation lab

    first testing logs shipped

    All requirements uptill MB4 including NS ones
    • should be complete at this stage
    • First full CD deployment either in the Member CD lab or the LF lab
    • 1st run of test cases and
    results shared
    • rest results logs automatically posted to LF CI servers  
    • All test cases
    planned for the release
    • have been executed
  • Test results published
    • (In case of CI / CD this waterfall approach is optional)
    • Failures and other issues have been documented
    MBI6
     Ad hoc reporting

     On going CI/CD

    based testing

    Critical issues fixed.

    Documentation complete (for third parties to recreate setup and run the tests)

    Not really a milestone but an on going reporting period

    Ad hoc reporting milestone is dependent on MBI6

    Unlike the other milestones this milestone is a continuous one that spans from the start of testing (MBI6) as long as required by the CI/CD process until the BP is ready for the Maturing review by the TSC.

    • All test cases and rest results logs automatically posted to LF CI servers  
     MBI5 Second community validation lab fully setup
    • Second community validation lab is identified and set up
    • This is non sequential and not dependent on any other MBI
    •  Peer Jenkins, BP HW and all necessary components setup ready to start testing of BP
     MBI6 BP successfully deployed in second community validation lab

     All test cases planned for the release have been executed .

    Deployment in second lab may result in CI/CD iterations of the BP depending on results/experiences with the second setup.

    Maturity Graduation reviewTSC conducts graduation review as per criteria set out in Remove This Page 2

    Request for graduation review made by PTL

    Decision of graduation made TSC

    TSC's Maturity Graduation review can have one of two outcomes:

    1. Project remains at 'Incubation' (i.e. the request to graduate wasn't approved by the TSC)
    2. Project graduates from 'Incubation' to 'Mature' (i.e. the request to graduate was approved by the TSC)
    • Complete the documentation
    • Critical issues fixed
    Sign-OffReleaseProject graduate to Mature stage