The graduation reviews are done by assessing the projects 



Project Name

MBI0

Kick-Off

(Project inducted to 'Incubation' by TSC)


MBI1

First regular community call held

MBI2

Planning complete

Identify integration/developers team & testing team

MBI2

MBI3

Integration Test plan created and shared with the community

Requirement/Feature Freeze (if applicable)

MBI3

MBI4

Scripts development and Set up accessible

Lab is set up for CD

MBI4


MBI5

Code Freeze (if applicable)

Additional test case development complete (

MBI5

MBI6

First deployment in validation lab

First test report logs shipped to LF CI servers

Ad hoc reporting

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

MBI6

MBI7

Second community validation lab identified

MBI7

MBI8

Second community validation lab fully setup

MBI8

MBI9

BP successfully deployed in second community validation lab

Graduation Review by TSC

(Request for graduation review made by PTL)

(Decision of graduation made TSC)

TSC's Graduation review can have one of two outcomes:

  1. Project remains at 'Incubation' (i.e. the request to graduate wasn't approved by the TSC)
  2. Project graduates from 'Incubation' to 'Mature' (i.e. the request to graduate was approved by the TSC)
1SDN Enabled Broadband Access (SEBA) for Network Cloud Blueprint FamilyxTarget date










Achieved date










2Serverless Blueprint Proposal for Addition to Network Cloud Blueprint FamilyxTarget date










Achieved date










3

Unicycle Blueprint Proposal for Addition to Network Cloud Blueprint Family

xTarget date










Achieved date










4

Rover Blueprint Proposal for Addition to Network Cloud Blueprint Family

xTarget date










Achieved date










5OVS-DPDK Unicycle Dell Blueprint ProposalxTarget date










Achieved date










6

NC-TF-BluePrint-ProposalAkraino Network Cloud and TF Integration

xTarget date










Achieved date










7Edge Video ProcessingxTarget date










Achieved date










8

ELIOT IoT Gateway Blueprint

xTarget date










Achieved date










9

ELIOT SD-WAN/WAN Edge/uCPE Blueprint

xTarget date










Achieved date










10

IEC Type 1 for Integrated Edge Cloud (IEC) Blueprint Family

xTarget date










Achieved date










11IEC Type 2 for Integrated Edge Cloud (IEC) Blueprint FamilyxTarget date










Achieved date










12

Industrial Edge (IE) Blueprint

xTarget date










Achieved date










13

Provider Access Edge (PAE) Blueprint

xTarget date










Achieved date










14

Radio Edge Cloud

xTarget date










Achieved date










15

StarlingX Far Edge Distributed Cloud

xTarget date










Achieved date










16

Time-Critical Edge Compute

xTarget date










Achieved date










17

Micro-MEC


Target date










Achieved date











CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED

...