Rel 2 Incubation stage reporting

 MBI = Milestone Bp Incubation

1) Entry Criteria:  MBI0. The project is approved to enter the 'Incubation' stage after TSC review and approval (Akraino Project Reviews)

2) Details of the Blue Print Milestones are in the slide attached

3) A Blueprint can be part of Rel 2 as a self certified project by fulfilling MBI0-MBI4

4) Some Blueprints who were already part of Rel 1 may seek graduation review by fulfilling MBI0-MBI6

3) Even though Milestones come one after the other, they need not be sequential and are not gating factors to enter the next or a subsequent stage. 

4) It is to be noted that a blue print does not need to be mature to be part of rel2,  and more particularly if the Blue Print was not part of Rel1, it cannot be mature in Rel 2 since it would not be part of two releases in rel2


The self Certification/ maturity graduation reviews are done by assessing the projects against the Incubation or Mature review as defined in the Akraino Project Reviews page.


Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.


Project Name

MBI0

Project Induction


MBI1

Kick Off

MBI2

Planning process defined


MBI3

CD Test Scripts developed

1st Validation Lab is Set up


MBI4

First Full CD deployment

BP is ready to download and deployable by users as self certified

Ad hoc reporting

CI/CD based testing and bug fixing


Ready for Rel 2 Incubation

Project Review

MBI5

Second community validation lab fully setup

MBI6

Ready for Maturity Review

Self Certification/Maturity Graduation Review as per BP Graduation Review Processes and Criteria

(Request for review made by PTL)

1uMECDec 2018Target date2019-09-022019-09-112019-10-012019-10-15




Achieved date2019-09-02







2

Target date








Achieved date








3



Target date








Achieved date








4



Target date








Achieved date








5

Target date








Achieved date








6

Target date








Achieved date








7

Target date








Achieved date








8

Target date








Achieved date








9

Target date








Achieved date








10

Target date








Achieved date








11

Target date








Achieved date








12

Target date








Achieved date








13

Target date