Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Akraino project reporting provides visibility of the each BP validation project (MB1, MB2 etc) and feature project (MF1, MF2 etc.by means of a set of defined milestones terms MB1, MB2 etc.terms 

The milestones are defined by the Documentation subcommittee.

Recording the milestones will be done the responsibility by each project PTL by so that the TSC can track project status.


1) Entry Criteria:  MB0 The project is approved to enter the incubation 'Incubation' stage as per the TSC guideline (Akraino Project Reviews)

...

4) There are sequential milestones (S) and non sequential milestones (NS). The non sequential milestones are guidelines to be completed at a certain stage, however they are not gating factors to enter the next stage. However the NS milestones also need to be completed at some point which will be marked as part of the relevant stage.

The graduation reviews are done by assessing the projects 


Project Name

MB0

Kick-Off

(Project inducted ti 'Incubation' by TSC)

MB1

Planning complete

Identify integration/developers team & testing team

MB2

Integration Test plan created and shared with the community

Requirement/Feature Freeze (if applicable)

MB3

Scripts development and Set up accessible

Lab is set up for CD


MB4

Code Freeze (if applicable)

Test

Additional test case development complete (

MB5

first

First deployment in validation lab

first testing

First test report logs shipped

MB6

to LF CI servers

Ad hoc reporting

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

Sign-Off (April 30th)

Release moved to mature

Graduation Review by TSC

Graduation outcome: can be the project is maintained at (a) its existing level (i.e. the request to graduate wasn't approved by the TSC) or (b) is graduated (i.e. the request to graduate was approved by the TSC):

  1. 'Incubation' to 'Mature', or
  2. 'Mature' to 'Core', or
  3. Any state to 'Archived'

(Decision of graduation made TSC)

(Request for graduation review made by PTL

(Decision of completion made by PTL and TSC

)


1SDN Enabled Broadband Access (SEBA) for Network Cloud Blueprint Familyx






2Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Familyx






3

Unicycle Blueprint Proposal for Addition to Network Cloud Blueprint Family

x






4

Rover Blueprint Proposal for Addition to Network Cloud Blueprint Family

x






5OVS-DPDK Unicycle Dell Blueprint Proposalx






6

NC-TF-BluePrint-ProposalAkraino Network Cloud and TF Integration

x






7Edge Video Processingx






8

ELIOT IoT Gateway Blueprint

x






9

ELIOT SD-WAN/WAN Edge/uCPE Blueprint

x






10

IEC Type 1 for Integrated Edge Cloud (IEC) Blueprint Family

x






11IEC Type 2 for Integrated Edge Cloud (IEC) Blueprint Familyx






12

Industrial Edge (IE) Blueprint

x






13

Provider Access Edge (PAE) Blueprint

x






14

Radio Edge Cloud

x






15

StarlingX Far Edge Distributed Cloud

x






16

Time-Critical Edge Compute

x






17

Micro-MEC













Project Name

M0 Kick-Off

M1

Planning

M2

Functionality freeze

M3

API Freeze

M4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery


Project Name

M0 MF0 Kick-Off

M1MF1

Planning

M2MF2

Functionality freeze

M3MF3

API Freeze

M4MF4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery

17

Akraino Blueprint Validation Framework

x







18

Akraino Portal Feature Project

x







19

Cluster Health & Overload Monitoring Platform (CHOMP) Feature Project

x







20

Support of OVS-DPDK in Airship

x







...